WARI-1601 Cement Integrity Assessment Tool RFP

Purpose
PTAC wishes to retain the services of a qualified research organization or consulting firm (the Contractor) with demonstrated experience in cased hole logging development and a strong understanding in fluid flow. Interested parties are invited to submit a proposal according to the specification provided herein.

Technology Background
A knowledge gap that has been identified is the lack of a tool that assesses integrity behind pipe well enough to identify the absence or presence of hydraulic isolation. The current cement bond log technology is adequate in showing the presence of cement, large channels within the cement, and areas of no cement. However, this technology unable to effectively detect minute channels in the cement that allow gas movement behind pipe, within the cement sheath and at the cement / bedrock interface. The quality of the data collected with the current technology is dependent on bond to pipe, weight of cement, channeling and bond to formation. There is also an inconsistency with respect to how the data is processed and presented. This inconsistency is evident when comparing different vendors cement bond logs and noise temperature logs. A new tool, enhanced data collection method or new assessment technology (collectively referred to as the “Tool”) that can identify the presence or absence of hydraulic isolation between the casing and the formation is needed for effective surface casing vent flow/gas migration source pathway identification, developing repair programs and also for identifying isolation issues at time of abandonment.

Project Scope
In the first phase, PTAC will retain the Contractor to develop this new Tool in a laboratory (bench scale) setting, and to develop an execution plan for field-based study. The second phase of this project would be the execution of a field-based study. An interim report will be due after the laboratory development portion of this study is complete. A Final Report will be required after completion of the field study. It should be assumed that a test well will be supplied by an industry partner facilitated through PTAC members.

Deliverables

  • Develop an execution plan and engage PTAC for an industry sponsor for the field-based study
  • Develop tool that will identify flow paths behind casing. The tool will need to be able to identify flow paths near the casing and also at the cement/formation interface.
  • Prepare and deliver Interim Report
  • Plan and execute a field based study as phase 2
  • Prepare and deliver the Final Report upon completion of phase 2
  • Prepare and deliver a summary presentation to a PTAC committee

Qualifications
The Contractor will have the following qualifications:

  • At least 10 years in the design, operations, servicing or consulting for oilfield cased hole logging;
  • Demonstrated experience with cased hole logging development;
  • Demonstrated understanding of fluid flow;
  • Demonstrated experience and skills at technology evaluation and report writing.

Contents of Proposals
The requested proposal should contain a very short description of the PTAC project and scope of work, CV or statement of qualifications and short excerpts of reports written by the applicant. The proposal document, which should be approximately 5 pages in length, addressing the following elements must be delivered electronically or by mail to PTAC by the deadline stated above:

  • Scope of work
  • Deliverables
  • Budget and execution schedules
  • Personnel assigned to the project
  • Qualifications (including cased hole logging/fluid flow knowledge and experience)
  • Disclosure of co-funding agreements or partnerships
  • Requested payment schedule, if any.

Budget and Schedule
The maximum budget is $200,000. The final report and all deliverables must be completed by December 31, 2017.

Confidentiality
The Contractor will be required to sign a confidentiality agreement related to the project. Disclosure of any project information will be at the discretion of PTAC. It is the intention of PTAC that key results and outcomes will eventually be made public.

RFP Schedule
April 5, 2017 – RFP re-issued
April 27, 2017 – Deadline for submission to PTAC
May 8, 2017 – Proposal selected by WARI.

Selection Process
PTAC has formed a Steering Committee for this project composed of industry stakeholders with relevant expertise pertaining to cement integrity assessment. PTAC will facilitate Steering Committee proceedings but will not be a decision-maker.

All submitted proposals will be provided to the Steering Committee for review. The Steering Committee will determine if proposals meet the requirements herein and provide an overall ranking based on Contractor qualifications and on proposal quality. The Steering Committee will make the final decision.

Once a selection of the best proposal according to the Steering Committee has been made, all submission contacts will be notified by email of the regarding the outcome of their individual proposal. The project final report will be shared on the PTAC website upon completion of the project.

Contact Information
Proposals should be submitted online using the following form: RFP Application Form